Highlands

Project Milestones

The project is moving along at a brisk pace. We will keep you informed of the progress as it happens. Watch this page regularly. We will even begin uploading pictures when we get into the development phase.


No.   Milestone Description   Status
1. General survey General survey of the land has been done. Completed
2. Legal scrutiny The legal scrutiny of entire 60 Acres plot has been done by our Legal consultant Mr. S Selvakumar. Completed
3. Procurement of Land Procurement of land has been done. Completed
4. Topographical Survey Topographical survey of the land has been done. Completed
5. Tie up with Jurong Tie up with Singapore based architect Jurong. Completed
6. Soft Launch at Bangalore April 13th, 2008
The Park
14/7 Mahatma Gandhi Road, Bangalore -India
Completed
7. Soft Launch at Dubai June 11th~13th, 2008
Four Seasons Hotel
Sheikh Zayed Road-Dubai
http://www.fourseasons.com/
Completed
8. Soft launch at Nepal July 03rd, 2008
Soaltee Crowne Plaza
Tahachal, Kathmandu - Nepal
http://www.ichotelsgroup.com
Completed
9. Soft launch at Colombo August 29th, 2008
Water Edges
Battaramulla -Sri Lanka
http://www.watersedge.lk/
Completed
10. Site Office September, 2008
Site Office @ Project
Site offece @ Project site at Mysore has been built
Completed
11. Development Work Approval for 12 acres, 12 guntas for development work
  • 1. December 26, 2009: Passed in the MUDA resolution
  • 2. May 25, 2010: Relinquishment Deed Signed
  • 3. June 03, 2010: Final approved plan signed by the Commissioner of MUDA

Approval for 12 acres, 8 guntas for development work
  • 1. July 28th, 2011: Passed in the MUDA resolution
  • 2. April 1st, 2011: Relinquishment Deed Signed
  • 3. April 7th, 2011: Final approved plan signed by the Commissioner of MUDA
Completed